The Horizon – Update 7
Model Center sign is installed. Please check the “Our Homes” page to view pictures of the completed Horizon Model Center.
Certificate of Occupancy obtainted from building officials – House completed! Welcome!
Landscaping around the pool is completed.
Frontyard landscaping is completed.
Installation of kick lighting under the master bathroom cabinets is completed.
Work on the front yard landscaping continues.
Back yard landscaping is completed.
Under cabinet lighting in the kitchen is installed.
Breakfast nook lighting fixture and living room ceiling fan installation is completed.
Ceiling fan and light fixtures are installed on the lanai.
Kitchen fan is installed.
Installation of the mirrors and light fixture in the foyer is completed.
Dining room light fixtures are installed.
Accent lighting is installed in the bedrooms.
Carpeting in the bedrooms is completed.
Stairs to the garage attic are installed.
Kitchen microwave is installed above the stove.